| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | |
Part of the full report. Unlock all 2 sections
| “smilee Celestial”Lapsed · completion date passed | Blue Valley Properties Pvt Ltd | Plot | – | Aug 2019 |
| 1 Lakhmulti Storey Housing DoddanagamangalaLapsed · completion date passed | Rajiv Gandhi Housing Corporation | Apartment | 323 sqft carpet (as filed) | Mar 2024 |
| 1 Lakhmulti Storey Housing GoolimangalaLapsed · completion date passed | Rajiv Gandhi Housing Corporation Pvt Ltd | Apartment | 323–484 sqft carpet (as filed) | Mar 2024 |
| A B AnanthaActive · 84% built | Amaravathi Builders | Apartment | 753–972 sqft carpet (as filed) | Jan 2027 |
| Abhee NandikaCompleted · OC 22-04-2022 | ABHEE DEVELOPERS | Apartment | 786 sqft carpet (as filed) | Completed |
| Abhee Prakruthi Villa PlotsCompleted (regulator flag) |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
₹99 for this report opens Valuation and Disputes & cases for this project, yours to read for good.
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
Source: K-RERA project page and the documents filed there, as read by us. 54 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
| Location & risks | – | 1 | 1 | Review |
|---|
| Construction & progress | – | – | 1 | Clear |
|---|
| Developer & finance |
|---|
| Developer | – | – | 1 | Clear |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| M/s.Abhee Developers |
| Plot |
| – |
| Completed |
| Abhee PrideCompleted · OC 18-04-2026 | ABHEE VENTURES PRIVATE LIMITED | Apartment | 688–842 sqft carpet (as filed) | Completed |
| Abhee Serenity SpringsActive · 35% built | Abhee Ventures | Apartment | 1,000–1,575 sqft | Jun 2030 |
8 of 235 other projects in Electronic City, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Vasuki Vallabha in the interactive atlas
Approval or registration
Khata issued
E Khatha · TMC, Bommasandra · Survey 63/3
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
Anekal Planning Authority · plan 1460/2023-24
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1251/308/PR/211125/008269
K-RERA registration ·
Approval or registrationThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Charges on the land | Not verified yet | |
|---|---|---|
| Developer's project loan | None declared | |
| Filed survey numbers matched to the KGIS map | 1 of 1 | |
|---|---|---|
| Matched part of the survey number | 1,761 sq m | |
| The whole survey number on the KGIS map | 8,443 sq m | |
| Extent the filed land schedule names for these survey numbers | 1,821 sq m | |
| Plot area against the filed extent | 0.97 times | |
| Land area filed with K-RERA | 1,821 sq m | |
| Village, hobli and taluk on the KGIS map | Bommasandra, Attibele-2 hobli, Anekal taluk | |
| Sketch dimensions | Not verified yet | |
| Sanctioned plan area | Not verified yet | |
| Mutation entry | Not verified yet | |
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
| Survey numbers | 63/3 | |
|---|---|---|
| Land extent, Sy 63/3 | 18 Guntas | |
| Area on the KGIS map | Not verified yet | |
| Land area of this registration | 1,821 sq m | |
| Khata | E Khatha · TMC, Bommasandra · 16 Feb 2024 | |
| Survey | Owners on the RTC | RTC extent | Filed extent | Extents agree? | Land category | Pending mutations |
|---|---|---|---|---|---|---|
| Sy. No. 63/3 | 3 | 18 guntas | 18 guntas | Yes | 0 |
| Building plan (Anekal Planning Authority) | Sanctioned 16 Jul 2024 · No. 1460/2023-24 | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire department | Filed with the registration | |
| SEIAA | Filed with the registration | |
| AAI | Filed with the registration | |
| KSPCB | Filed with the registration | |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 31 Dec 2027 |
| Land conversion | Declared not converted | |
|---|---|---|
| Survey numbers | 63/3 |
₹99 for this report opens Valuation and Disputes & cases for this project, yours to read for good.
Map of the ground within about 450 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Residential (main) | Clear |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | 5.9 km, G K LAYOUT | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | 90 m to the north-east, Kammasandra Lake2 | |
| Height above nearest drain | Not verified yet | |
| Amenities declared | Electricity · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Electricity, built | 0% | |
| Gym, built | 0% | |
| Power Backup, built | 0% | |
| Kitchen handover | Not verified yet | |
| Covered parking per unit | 1.00 (32 covered spaces for 32 units) | |
| Sewage plant | Not verified yet | |
| Power backup | Declared by the promoter | |
As the promoter reported it

| Main structure | 100% · planned by 15 Jul 2025 | |
|---|---|---|
| Electrical and plumbing finishing | 60% · planned by 15 Apr 2026 | |
| Internal roads | Not verified yet | |
| Club house | Not verified yet | |
| Completion | 88% | |
| Completion, accountant | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | 31 Dec 2027 | |
| RERA completion date | 31 Dec 2027 | |
| Work began, as filed | 1 Oct 2024 | |
| Structure | Not verified yet | |
|---|---|---|
| Foundation | Not verified yet | |
| Wall material | Not verified yet | |
| Wall thickness | Not verified yet | |
| Concrete / steel grade | Not verified yet | |
| Building heights, fire NOC | 14.95 m filed | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | Not verified yet | |
|---|---|---|
| Flooring | Not verified yet | |
| Toilet tiles, spec vs brochure | Not verified yet | |
| Wiring | Not verified yet | |
| Sanctioned load per flat | Not verified yet | |
| Power backup | Provided, 10 sq m | |
| Sewage plant | Not verified yet | |
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Form 6 · Mar 2026, May 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | Not verified yet | |
| Environmental clearance | Not verified yet | |
| Architect, quarterly | Form 5 · Mar 2026, May 2026, Jul 2026, Oct 2026 (4 filed) | |
| Chartered accountant, Form 4 | Dated 14 Jul 2026 | |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹2.52 Cr 25.9%Development · ₹7.22 Cr 74.1%
| Estimated cost | ₹9.75 Cr | |
|---|---|---|
| Cost incurred | ₹5.98 Cr | |
| Cost left | ₹1.89 Cr | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | ₹1.68 Cr | |
| Land cost revision | Not verified yet | |
Sold (10) 31.3%Unsold (22) 68.8%
| Sold, Q3 2025-26 | 3 / 32 · 29 available | |
|---|---|---|
| Sold, Q4 2025-26 | 3 / 32 · 29 available | |
| Sold, Q1 2026-27 | 6 / 32 · 26 available | |
| Sold, Q2 2026-27 | 10 / 32 · 22 available | |
| Unsold, Q2 2026-27 | 22 | |
| Sold in Q4 2025-26 | 0 | |
| Sold in Q1 2026-27 | 3 | |
| Sold in Q2 2026-27 | 4 | |
| Flats booked, Form 4 Q1 2026-27 | 6 |
| Escrow bank | STATE BANK OF INDIA · GIRINAGAR | |
|---|---|---|
| Designated account, collected | ₹70.6 L in Q2 2026-27 | |
| Designated account, withdrawn | ₹76.0 L in Q2 2026-27 | |
| Amount withdrawable, Form 4 | ₹5,98,12,241 | |
| Net amount withdrawable, Form 4 | ₹3,52,69,721 | |
| Withdrawn from the escrow account to date | ₹2,45,42,520 | |
| Share of collections deposited in escrow | 65.22% | |
| Sale proceeds realised, Q1 2026-27 | ₹2,93,05,006 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| Other phases under this promoter name | 263 | |
|---|---|---|
| With a filed extension or completion | 120 (86 completed, 34 extended) | |
| Average schedule slip | 10 months |
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan | Sanctioned 16 Jul 2024 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | STATE BANK OF INDIA · GIRINAGAR | |

Map of storm drains, lakes and government-flagged flood locations within about 450 m of the site.
Ten-year July mean for this taluk: 28.7 m
Across Anekal, the water table sat 21.3 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 28.7 m, and it recovered 3.3 m over the year.
| Groundwater | Anekal taluk average, July 2023: 21.3 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 21.3 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell, Local authority (Purasabhe Bommasandra) | |
| Nearest city water main | 2.2 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | None within 3 km | |
| Ground level | Not verified yet | |
| Metro, operational | 650 m, Hebbagodi | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 55.9 | 61 | 41.6 |
| MG Road (CBD) | 21.6 | 29 | 19.0 |
| Manyata Tech Park | 32.2 | 39 | 25.4 |
| ITPL, Whitefield | 24.5 | 33 | 18.7 |
| Ecospace, Bellandur ORR | 16.6 | 23 | 11.1 |
| Electronic City Ph 1 | 3.9 | 7 | 1.7 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | 2.0 km to the south | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 740 m to the west |