| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | 1 | – | Review |
| Approvals | 1 | – | – | Red flag |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | ||
| Bhavisha MeadowsLapsed · completion date passed | BHAVISHA PROPERTIES | Apartment | – | Mar 2023 |
| CelestaCompleted · OC 04-03-2023 | GLOBAL EDIFICE BUILDERS | Apartment | 370–724 sqft carpet (as filed) | Completed |
| Dhiraan Urban ForestCompleted · OC 18-04-2024 | DHIRAAN INFRASTRUCTURE PVT LTD | Apartment | 460–970 sqft carpet (as filed) | Completed |
| Fortuners Infra ElixirRegistered · no quarterly update yet | FORTUNERS INFRA | Apartment | 418–864 sqft carpet (as filed) | Sep 2026 |
| Green Apple HikesCompleted · OC 27-01-2021 | GLOBAL EDIFICE DEVELOPERS AND BUILDERS | Apartment | 872 sqft carpet (as filed) | Completed |
| Green VistaCompleted (regulator flag) | BEST PROPERTIES | Plot | – | Completed |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
Source: K-RERA project page and the documents filed there, as read by us. 9 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| – |
| Not verified |
| Location & risks | – | 2 | – | Review |
|---|
| Construction & progress | 1 | – | – | Red flag |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | 1 | – | Review |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| High Classic DelightCompleted (regulator flag) | M/s HIGH CLASSIC BUILDERS AND DEVELOPERS | Plot | ~1,130–1,200 sqft (estimate: filed carpet plus 25%) | Completed |
| Jr Meadows Phase 3Completed (regulator flag) | JR Housing Developers Pvt Ltd | Plot | – | Completed |
8 of 18 other projects in Chandapura, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open The Nashville in the interactive atlas
Transfer of the land
Sale deed
Survey 36/3
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
Local Planning Authority · plan CC/308/2016-17
K-RERA filing, approvals
Approval or registration
Khata issued
A Khatha · NA · Survey 36/3
K-RERA filing, land schedule
Approval or registration
RERA registration
PRM/KA/RERA/1251/308/PR/100522/004863
K-RERA registration ·
Transfer of the landApproval or registrationTitle checkThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Title opinion | Not verified yet | |
|---|---|---|
| Records searched to | 9 Mar 2022 | |
| Court-case search | Not verified yet | |
| High Court order | Not verified yet | |
| Charges on the land | Not verified yet | |
|---|---|---|
| Developer's project loan | None declared | |
| Mortgage on the project land | None declared | |
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Survey numbers | 36/3 | |
|---|---|---|
| Land extent, Sy 36/3 | 5,427 sq m | |
| Area on the KGIS map | Not verified yet | |
| Land area of this registration | 5,427 sq m | |
| Khata | A Khatha · NA · 16 Mar 2022 | |
| Sale deed | Dated 14 Nov 2013 | |
| Title deed | Consideration ₹81.0 L · Sy 36/3; 36/1, Attibele hobli · 1-00 Acre | |
| Building plan (Local Planning Authority) | Sanctioned 11 Aug 2021 · No. CC/308/2016-17 | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire department | Filed with the registration | |
| SEIAA | Filed with the registration | |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | Filed with the registration | |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 10 | |
| RERA completion date | 11 Mar 2024 |
| Land conversion | Declared not converted | |
|---|---|---|
| Survey numbers | 36/3 |
₹99 for this report opens Contract & costs and Disputes & cases for this project, yours to read for good.
₹99 for this report opens Contract & costs and Disputes & cases for this project, yours to read for good.
2 BHK Flats · avg 79 m² 61.4%3 BHK Duplex · avg 158 m² 38.6%
| Type | Flats | Carpet per flat, average (sq ft) |
|---|---|---|
| 2 BHK Flats | 54 | 850 |
| 3 BHK Duplex | 34 | 1,701 |
| Signature Heights | about 2.5 km | Locked | |
|---|---|---|---|
| Abhee Serenity Springs | 2.9 km | Locked | |
| Columbia Aaltius | about 3 km, to a locality centre | Locked | |
| Sobha Hamptons -Townpark Phase 1 W4 To 6 | about 3 km | Locked |
| The Nashville This project | This project is the point the others are measured from | 11 Mar 2024 | Not filed | Not verified yet |
|---|---|---|---|---|
| Signature Heights | about 2.5 km | 31 Oct 2028 | 51% (178 of 346) | Locked |
| Abhee Serenity Springs | 2.9 km | 30 Jun 2030 | 38% (110 of 288) | Locked |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Parks & open space, at the filed pin | Review |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | 11.1 km, G K LAYOUT | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | 140 m to the east, an unnamed pond | |
| Height above nearest drain | Not verified yet | |
| Amenities declared | Electricity · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Kitchen handover | Not verified yet | |
| Covered parking per unit | 1.13 (99 covered spaces for 88 units) | |
| Sewage plant | Not verified yet | |
| Power backup | Declared by the promoter | |
| Possession, agreement | 11 Mar 2024 | |
|---|---|---|
| Schedule end | 10 Mar 2024 | |
| RERA completion date | 11 Mar 2024 | Red flag |
| Work began, as filed | 11 Aug 2021 |
| Structure | Not verified yet | |
|---|---|---|
| Foundation | Not verified yet | |
| Wall material | Not verified yet | |
| Wall thickness | Not verified yet | |
| Concrete / steel grade | Not verified yet | |
| Building heights, fire NOC | 14.95 m filed, 2 towers | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | Not verified yet | |
|---|---|---|
| Flooring | Not verified yet | |
| Toilet tiles, spec vs brochure | Not verified yet | |
| Wiring | Not verified yet | |
| Sanctioned load per flat | Not verified yet | |
| Power backup | Provided, 21 sq m | |
| Sewage plant | Not verified yet | |
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Not verified yet | |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | Not verified yet | |
| Environmental clearance | Not verified yet | |
| Engineer's certificate, registration | Dated 28 Apr 2022 | |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹2.50 Cr 12.8%Development · ₹17.00 Cr 87.2%
| Estimated cost | ₹19.50 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹17.00 Cr | |
| Cost incurred | Not verified yet | |
| Cost left | Not verified yet | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
| Escrow bank | Industrial Development Bank of India · HSR LAYOUT | |
|---|---|---|
| Designated account, collected | Not verified yet | |
| Designated account, withdrawn | Not verified yet | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 10 | |
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | 9 Mar 2022 | Review |
| Building plan | Sanctioned 11 Aug 2021 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | Industrial Development Bank of India · HSR LAYOUT | |
Map of 2 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Abhee Serenity Springs, price locked; SOBHA Townpark, price locked.
| Sobha Madison Heights-Townpark Phase 1 W5 To 7 | about 3 km | Locked |
|---|
| Sobha Madison Heights-Townpark Phase 2 W1 To 4 | about 3 km | Locked |
|---|
| SOBHA Townpark | 3.5 km | Locked |
|---|
| Sobha Brooklyn Towers - Town Park Phase 5, W3 | about 3.5 km | Locked |
|---|
| Sobha Brooklyn Towers - Town Park Phase 1, W1 | about 3.5 km | Locked |
|---|
| Sobha Brooklyn Towers - Town Park Phase 3, W5 | about 3.5 km | Locked |
|---|
| Sobha Brooklyn Towers - Town Park Phase 4, W4 | about 3.5 km | Locked |
|---|
| Sobha Manhattan Towers-Town Park Phase 1 W 4 & 5 | about 3.5 km | Locked |
|---|
| Columbia Aaltius |
|---|
| about 3 km, to a locality centre |
| 30 Sep 2026 |
| 54% (89 of 165) |
| Locked |
| Sobha Hamptons -Townpark Phase 1 W4 To 6 | about 3 km | 30 Jun 2031 | 47% (230 of 492) | Locked |
|---|
| Sobha Madison Heights-Townpark Phase 1 W5 To 7 | about 3 km | 31 Dec 2030 | 73% (348 of 480) | Locked |
|---|
| Sobha Madison Heights-Townpark Phase 2 W1 To 4 | about 3 km | 31 Dec 2032 | 84% (540 of 640) | Locked |
|---|
| Rent, 3BHK, 3 km | ₹18,000 /mo · 5 listings | |
|---|---|---|
| Rent, 2BHK, 3 km | ₹20,000 /mo · 9 listings | |
| Rent per sq ft, 3 km | ₹19.2 /mo, as listed · 11 listings with a size | |
| Gross yield | Not verified yet | |
| Gross yield, per sq ft | Not verified yet | |
| Bengaluru median yield | Not verified yet | |
| Projects within 4 km, counted | 28 (18 with an approximate location) | |
|---|---|---|
| Flats in them | 14,839 | |
| Booked | 5,443 of 14,839 (37%) | |
| Unsold | 9,396 | |
| Booked a month, pooled | 60 flats | |
| Months to sell, pooled | 157 months |
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 28.7 m
Across Anekal, the water table sat 21.3 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 28.7 m, and it recovered 3.3 m over the year.
| Groundwater | Anekal taluk average, July 2023: 21.3 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 21.3 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell | |
| Nearest city water main | 7.3 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | None within 3 km | |
| Ground level | Not verified yet | |
| Metro, operational | 4.4 km, Bommasandra | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 59.7 | 65 | 45.9 |
| MG Road (CBD) | 25.4 | 34 | 24.2 |
| Manyata Tech Park | 36.0 | 44 | 30.4 |
| ITPL, Whitefield | 29.2 | 34 | 22.3 |
| Ecospace, Bellandur ORR | 20.5 | 30 | 15.9 |
| Electronic City Ph 1 | 7.7 | 11 | 6.9 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | 2.1 km to the north-west | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 1.2 km to the north-west, named Surya City on OpenStreetMap |