Overview
Vanasiri Badavane
Part ofVanasiri Badavane2 phases, 242 flats
Overview
Part ofVanasiri Badavane2 phases, 242 flats
Overview
Part ofVanasiri Badavane2 phases, 242 flats
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Aashirvad Siddhi PriyaFiled as completed · no completion certificate on record | SEENAPPA P | Plot | ~600–1,240 sqft (estimate: filed carpet plus 25%) | Nov 2024 |
| Aditya OrchardLapsed · completion date passed | Mangala Raghavan | Plot | ~1,200–1,800 sqft (estimate: filed carpet plus 25%) | May 2024 |
| Aprameya Brindavanam EliteCompleted (regulator flag) | Aprameya Properties Pvt Ltd | Plot | – | Completed |
| Ashwasurya Atharva RitewayCompleted (regulator flag) | RITEWAY & KUBERA PROMOTERS | Plot | ~1,200–2,400 sqft (estimate: filed carpet plus 25%) | Completed |
| Axis Banyan CountyCompleted (regulator flag) | R.Harish babu | Plot | – | Completed |
| Birla Apple SpireLapsed · completion date passed | Apple spire India LLP | Apartment |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
Source: K-RERA project page and the documents filed there, as read by us. 9 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Satellite map with the 3 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 3 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. The drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
| Location & risks | – | 1 | 1 | Review |
|---|
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| 1,667 sqft carpet (as filed) |
| Sep 2019 |
| BloomfieldsActive · 85% built | Shravan Gupta | Plot | ~600–2,400 sqft (estimate: filed carpet plus 25%) | Apr 2029 |
| BlossomCompleted · OC 11-07-2024 | BRUHASPATI BUILDERS LLP | Apartment | 309 sqft carpet (as filed) | Completed |
8 of 101 other projects in Mysore Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Vanasiri Badavane in the interactive atlas
Transfer of the land
Title deed executed
Consideration ₹1.54 Cr · Sy 186/2, Kambipura village, Kengeri hobli, Bangalore South taluk · 2 Acres 07 Guntas
Title deed filed with K-RERA, pp. 1, 5, 10 · See it in Documents
Transfer of the land
Title deed executed
Consideration ₹2.18 Cr · Sy 186/1, Kambipura village, Kengeri hobli, Bangalore South taluk
Title deed filed with K-RERA, pp. 1, 5, 11 · See it in Documents
Transfer of the land
Sale deed
Survey 186/1, 186/2
K-RERA filing, land schedule
Approval or registration
Khata issued
A Khatha · TAHASILDHAR, BANGALORE SOUTH TALUK · Survey 186/1, 186/2
K-RERA filing, land schedule
Approval or registration
Land use converted
DEPUTY COMMISSIONER, BANGALORE · Survey 186/1, 186/2
K-RERA filing, land schedule
Transfer of the land
Title deed registered
No. KEN-1-08700-2013-14 · Book 1 · executed 27 Nov 2013 · Consideration ₹3.05 Cr · Sy 185/2, Kambipura village, Kengeri hobli, Bangalore South taluk
Title deed filed with K-RERA, pp. 1, 5, 8, 10 · See it in Documents
Transfer of the land
Sale deed
Survey 185/2
K-RERA filing, land schedule
Transfer of the land
Title deed executed
Consideration ₹92.5 L · Sy 187; 187/3, Kambipura village, Kengeri hobli, Bangalore South taluk
Title deed filed with K-RERA, pp. 1, 5, 10 · See it in Documents
Transfer of the land
Sale deed
Survey 187/3
K-RERA filing, land schedule
Approval or registration
Khata issued
A Khatha · TAHASILDHAR, BANGALORE SOUTH TALUK · Survey 185/2
K-RERA filing, land schedule
Approval or registration
Khata issued
A Khatha · TAHASILDHAR, BANGALORE SOUTH TALUK · Survey 187/3
K-RERA filing, land schedule
Approval or registration
Land use converted
DEPUTY COMMISSIONER, BANGALORE · Survey 187/3
K-RERA filing, land schedule
Approval or registration
Land use converted
DEPUTY COMMISSIONER, BANGALORE · Survey 185/2
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BDA · plan BDA/TPM/PRL-05-2015-16/4164/2015-16
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1251/310/PR/060422/004820
K-RERA registration ·
Transfer of the landApproval or registrationThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Charges on the land | Not verified yet | |
|---|---|---|
| Developer's project loan | Private lender (individual) · ₹14.00 Cr disbursed | |
| Mortgage on the project land | None declared | |
| Filed survey numbers matched to the KGIS map | 3 of 3 | |
|---|---|---|
| Whole survey numbers on the KGIS map | 53,637 sq m | |
| Extent the filed land schedule names for these survey numbers | 32,918 sq m | |
| Plot area against the filed extent | 1.63 times | |
| Village, hobli and taluk on the KGIS map | K.G.Kambipura, Kengeri-2 hobli, Bangalore-South taluk | |
| Sketch dimensions | Not verified yet | |
| Sanctioned plan area | Not verified yet | |
| Mutation entry | Not verified yet | |
Satellite map with the 3 cadastral survey plots named in the filing outlined. The outline is the land, not the building. All 3 filed survey numbers matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026. The drawn plots are whole survey numbers, not the project's own share of them; they show where the land is, not the site.
| Survey numbers | 185/2, 186/1, 186/2, 187/3 | |
|---|---|---|
| Area on the KGIS map | Not verified yet | |
| Khata | A Khatha · TAHASILDHAR, BANGALORE SOUTH TALUK · 11 Feb 2014; A Khatha · TAHASILDHAR, BANGALORE SOUTH TALUK · 21 May 2012; A Khatha · TAHASILDHAR, BANGALORE SOUTH TALUK · 30 May 2014 | |
| Sale deed | Dated 27 Feb 2012, 27 Nov 2013, 22 Jan 2014 | |
| Title deed | Sy 14/6, Kambipura village, Kengeri hobli, Bangalore South taluk · 0-28 Guntas; Sy 187, Kambipura village, Kengeri hobli, Bangalore South taluk | |
| Sy. No. 185/2 | 1 | 2 acres 33 guntas | 2 acres 33 guntas | Differs: 1 acre 24 guntas apart | 0 | |
| Sy. No. 186/1 | 1 | 3 acres 3 guntas | 0 | |||
| Sy. No. 186/2 | 1 | 2 acres 7 guntas | 0 | |||
| Sy. No. 187/3 | 1 | 37 guntas | 0 guntas | Differs: 3 acres 24 guntas apart | 0 |
| Building plan (BDA) | Sanctioned 10 Feb 2016 · No. BDA/TPM/PRL-05-2015-16/4164/2015-16 | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire department | Filed with the registration | |
| SEIAA | Filed with the registration | |
| AAI | Filed with the registration | |
| KSPCB | Filed with the registration | |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 31 Oct 2022 |
| Land conversion | 4 of 4 parcels converted | |
|---|---|---|
| Sy 185/2 | Converted 16 Dec 2015 · DEPUTY COMMISSIONER, BANGALORE | |
| Sy 186/1, 186/2 | Converted 27 Mar 2013 · DEPUTY COMMISSIONER, BANGALORE | |
| Sy 187/3 | Converted 16 Feb 2015 · DEPUTY COMMISSIONER, BANGALORE | |
| Survey numbers | 185/2 · 186/1 · 186/2 · 187/3 |
₹99 for this report opens Contract & costs and Disputes & cases for this project, yours to read for good.
₹99 for this report opens Contract & costs and Disputes & cases for this project, yours to read for good.
| Good Earth Cadence | 1.0 km | Locked | |
|---|---|---|---|
| Good Earth Ochre | 1.7 km | Locked | |
| Samaya Sunshine | about 6 km | Locked | |
| Sumadhura Pramoda | about 8 km | Locked |
| Vanasiri Badavane This project | This project is the point the others are measured from | 31 Oct 2022 | Not filed | Not verified yet |
|---|---|---|---|---|
| Good Earth Cadence | 1.0 km | 31 Dec 2028 | 72% (104 of 145) | Locked |
| Good Earth Ochre | 1.7 km | 31 Oct 2027 | 92% (35 of 38) | Locked |
| Samaya Sunshine |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Residential (main), at the filed pin | Clear |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | 3.9 km, Kengeri Yellamma temple | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | 2.0 km to the north-east, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | 570 m to the south-east, an unnamed pond | |
| Height above nearest drain | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | Not verified yet | |
| RERA completion date | 31 Oct 2022 | |
| Work began, as filed | 1 Apr 2019 | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Not verified yet | |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | Not verified yet | |
| Environmental clearance | Not verified yet | |
| Architect's certificate, registration | Dated 10 Dec 2021 · site inspected 10 Nov 2021 | |
| Engineer's certificate, registration | Dated 4 Feb 2022 | |
| Chartered accountant's certificate, registration | Dated 1 Feb 2022 | |
Land · ₹8.73 Cr 54.9%Development · ₹7.17 Cr 45.1%
| Estimated cost | ₹15.91 Cr | |
|---|---|---|
| Estimated cost, architect's and engineer's certificates | ₹7.17 Cr | |
| Cost incurred | Not verified yet | |
| Cost left | Not verified yet | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
| Escrow bank | Karnataka State Co-operative Apex Bank Ltd. · CHANDRA LAYOUT, BANGALORE | |
|---|---|---|
| Designated account, collected | Not verified yet | |
| Designated account, withdrawn | Not verified yet | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| Developer's project loan | Private lender (individual) · ₹14.00 Cr disbursed | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan (BDA) | Sanctioned 10 Feb 2016 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | Karnataka State Co-operative Apex Bank Ltd. · CHANDRA LAYOUT, BANGALORE | |
Map of 2 projects within 4 km of the site that have a price confirmed from their Form 4 certificate: Good Earth Cadence, price locked; Good Earth Ochre, price locked.
| Axis Amarissa | about 8.5 km | Locked |
|---|
| Jhanavi Trishul Alaska | 8.5 km | Locked |
|---|
| Harivishram | about 9 km | Locked |
|---|
| Sattva Springs | about 9.5 km | Locked |
|---|
| Mahindra Eden Phase-2 | about 9.5 km | Locked |
|---|
| Sobha Royal Crest | about 10 km | Locked |
|---|
| Garden Square | 9.9 km | Locked |
|---|
| Srivara Vasudha | about 10 km | Locked |
|---|
| about 6 km |
| 31 Dec 2026 |
| 33% (8 of 24) |
| Locked |
| Sumadhura Pramoda | about 8 km | 31 Dec 2029 | 50% (148 of 297) | Locked |
|---|
| Axis Amarissa | about 8.5 km | 31 Dec 2029 | 28% (23 of 81) | Locked |
|---|
| Jhanavi Trishul Alaska | 8.5 km | 30 Sep 2028 | 32% (47 of 148) | Locked |
|---|
| Rent, 3BHK, 3 km | ₹28,000 /mo · 5 listings | |
|---|---|---|
| Rent, 2BHK, 3 km | ₹24,150 /mo · 5 listings | |
| Rent per sq ft, 3 km | ₹25.9 /mo, as listed · 11 listings with a size | |
| Gross yield | Not verified yet | |
| Gross yield, per sq ft | Not verified yet | |
| Bengaluru median yield | Not verified yet | |
| Projects within 4 km, counted | 17 (4 with an approximate location) | |
|---|---|---|
| Flats in them | 5,017 | |
| Booked | 2,570 of 5,017 (51%) | |
| Unsold | 2,447 | |
| Booked a month, pooled | 34 flats | |
| Months to sell, pooled | 72 months |
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 23.2 m
Across Bengaluru South, the water table sat 16.9 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 23.2 m, and it fell 4.2 m over the year.
| Groundwater | Bengaluru South taluk average, July 2023: 16.9 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 16.9 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell, Local authority (Kumbalagodu Gram Panchayath) | |
| Nearest city water main | 3.9 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | 2.0 km to the north-east, tertiary drain | |
| Ground level | Not verified yet | |
| Metro, operational | 2.5 km, Challaghatta | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 55.0 | 60 | 45.0 |
| MG Road (CBD) | 22.2 | 29 | 19.3 |
| Manyata Tech Park | 32.6 | 39 | 25.9 |
| ITPL, Whitefield | 39.4 | 47 | 32.9 |
| Ecospace, Bellandur ORR | 34.0 | 38 | 25.0 |
| Electronic City Ph 1 | 30.8 | 28 | 24.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | 1.5 km to the north, named STP-6 on OpenStreetMap | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 180 m to the south-west, named Kambipura Substation on OpenStreetMap |